Pile Driving Completed At Site For New Airport

October 9, 2017

The ‘loudest phase’ of the construction for the airport redevelopment project has been completed ahead of schedule, Skyport said today, explaining that all 719 piles have been driven beneath the surface to create the foundation for the new terminal.

“The pile driving began on May 28 and work took place seven days a week. Pile driving is the process of hammering steel piles into the ground at a depth of 115 feet within the footprint of the new terminal and passenger bridges. It was essential for supporting the structure of the new terminal,” Skyport said.

Piling Bermuda Oct 9 2017 (1)

Frank Ross, Executive Director, Infrastructure, Aecon Construction, says: “The pile driving was the noisiest phase of the project and we would like to thank our stakeholders and neighbours for being patience for the past couple of months.

“We are pleased to have completed it months ahead of schedule. Also, so far, 34% of the pile caps have been completed and we are well on our way to finishing the project on time.”

Piling Bermuda Oct 9 2017 (2)

“The work was scheduled between 7am and 10pm every Monday through Saturday with work also taking place between 7am and 6pm on Sundays,” Skyport said.

“The schedule was designed to ensure that the piling work is completed in as short of a time as possible, to minimise the impact on area residents and businesses. The steel piles were installed with two rigs, both using the hammer method.

“Pile driving finished on September 22, some four months ahead of the schedule. Work was carried out by Aecon Foundations and Correia Construction. Twenty-eight Bermudians were involved in the pile driving works.

Piling Bermuda Oct 9 2017 (3)

“The construction of the new airport terminal is expected to take 40 months to complete and will be finished in 2020.”

- Photos courtesy of Robert Daniels

airplane click here copy (1)

Read More About

Category: All, News

Comments (10)

Trackback URL | Comments RSS Feed

  1. reminds me of.... says:

    The bus ly-by at Dev Rec–Will be completed on time, to spec and within budget!!

  2. The real Terry says:

    4 months ahead of schedule, obviously the PLP had nothing to do with this LOL

    • Triangle Drifter says:

      Sad but true.

      • Serious Though says:

        They Own it for 30 yrs , the faster they build it better for their bottom line.$$$. … nothing to do with PLP or OBA

        • Wahoo says:

          Well de taxpayer get a little pissed wben they see it take 5 weeks to put up 6 course of block.

        • Zevon says:

          Proof that private enterprise is more efficient.

  3. The Kid says:

    Thanks Bob……

  4. BermyFoxy says:

    I’ve heard through a friend who knows a pilot, that with the position of the new terminal, it will make the emergency runway useless. Thus, planes will have to start carrying more fuel for emergencies and in turn will increase the prices of airline tickets to and from Bermuda.