RTN For Publication: Fractious Street & North Shore Road, Hamilton Parish – 2021 March 15 To April 30

  • Notice Type: Government Notice
  • Notice Sub Type: Traffic Notice
  • Notice ID: GN0195/2021
  • Public Authorities / Department: Public Works Headquarters
  • Publication Date: 01 March 2021

Ministry Of Public Works

Road Traffic Act 1947

Fractious Street & North Shore Road Hamilton Parish Road & Lane Closure For Belco Trench Work

Monday, March 15th, 2021 through to Friday, April 30th, 2021

The Ministry of Public Works wishes to inform motorists that BELCO’s trench work along the Railway trail at Bailey’s Bay has reached North Shore Road. Work will stop here temporarily and all efforts will be redirected to Fractious Street at BELCO’s substation. Trenching down Fractious Street from Fractious Drive to North Shore Road will be in the center of the road which will require a full road closure to be imposed for this section. Consequently once the trench reaches North Shore Road a lane closure will be encouraged to cross over into the eastbound lane and tie into the Bailey’s Bay Ramp.

It is estimated that the Fractious Street trench work will be ongoing for one month before proceeding into North Shore Road.

The lane & road closures will commence Monday, March 15th, 2021 to Friday April 30th, 2021. Working hours will be from 8:00 am to 6:00 pm, weekly Monday through Sunday.

The public is asked to use alternative routes via Trinity Church Road & Harrington Sound Road whilst the north end of Fractious Street is closed. Access to Fisherman’s Hill and Fractious Drive will have to be from the south end of Fractious Street via Wilkinson Avenue. Motorists and joggers are advised to exercise extreme caution when passing this wide construction area to protect themselves and construction workers on site.

Traffic controls will be under the direction of BELCO, Island Construction Ltd. and Works & Engineering representatives, and will be managed through traffic control signals and directional signs.

The Ministry of Public Works wishes to encourage the full cooperation of the public and apologizes for any inconvenience that may result.

Should there be any questions regarding these works, please direct queries to the attention of Jonathan Pedro, Project Manager for BELCO at 295-5111 ext. 1441 and for traffic control queries to the attention of Tina Beer-Searle, Civil Engineer Highways for the Ministry of Public Works on 501-3044.

By Order_____________________________________________________________

Lt. Col. the Hon. David A. Burch OBE [Mil] ED, JP, MP

Minister of Public Works

testimonial-divider

RTN For Publication: Stokes Point Road And Mullet Bay Road To Echo Lane – Lane Closure – 2021 March 15 To June 14

  • Notice Type: Government Notice
  • Notice Sub Type: Traffic Notice
  • Notice ID: GN0194/2021
  • Public Authorities / Department: Public Works Headquarters
  • Publication Date: 01 March 2021

Ministry Of Public Works

Road Traffic Act 1947

Stokes Point Road And Mullet Bay Road To Echo Lane, St. George’s Lane Closures For Belco Trench Works

Monday, March 15th, 2021 Through To Monday, June 14th, 2021

The Ministry of Public Works wishes to inform motorists that Stokes Point Road and Mullet Bay Road to Echo Lane junction in St. George’s will undergo trench work that will require a one-lane closure. This trench work will commence at the west end of Stokes Point Road near the bridge and head towards Mullet Bay Road in the westbound lane. From there it will crossover Mullet Bay Road and head down the eastbound lane until it reaches Echo Lane at Ferry Reach Road.

For Stokes Point Road, a detour route for emergency services will be posted via a private driveway. Trash pick-up will commence as normal and the contractor will place trash at a temporary trash pickup location near the junction of Stokes Point Road and Mullet Bay Road.

All residents will be granted access to Stokes Point Road and are advised not to park on Stokes Point Road at any time.

The lane closure will take place during Monday, March 15th, 2021 through Monday, June 14th, 2021. Working hours will be from 7:30 am to 6:00 pm, weekly from Monday through Sunday and trench work should reach 200 feet section lengths at a time.

Motorists are asked to use caution when passing the open trench since it may near to the center yellow line and can be quite deep.

Traffic controls will be under the direction of D&J Construction Co. Ltd. and Ministry of Public Works representatives and will be managed through traffic control signs.

The Ministry of Public Works wishes to encourage the full cooperation of the public and apologizes for any inconvenience that may result.

Should there be any questions regarding these works, please direct queries to the attention of Mr. Jonathan Pedro, Project Manager for BELCO at 295-5111 ext. 1441. Any queries on traffic control should be directed to Tina Beer-Searle, Civil Engineer Highways for Ministry of Public Works on 501-3044.

By Order____________________________________________________

Lt. Col. the Hon. David A. Burch OBE [Mil] ED, JP, MP

Minister of Public Works

testimonial-divider

RTN For Publication: Harrington Sound Road Phase Ii Lane Closure – 2021 March 9 – September 26

  • Notice Type: Government Notice
  • Notice Sub Type: Traffic Notice
  • Notice ID: GN0193/2021
  • Public Authorities / Department: Public Works Headquarters
  • Publication Date: 01 March 2021

Ministry Of Public Works

Road Traffic Act 1947

Harrington Sound Road Hamilton Parish Lane Closure For Belco Trench Works – Phase II

Tuesday, March 9th, 2021 – Sunday, September 26th, 2021

The Ministry of Public Works wishes to inform motorists that the ongoing BELCO trenching project on Harrington Sound Road in Hamilton Parish will require an extension to the one lane closure for Phase II of the project taking this into Flatts.

This lane closure will be on Harrington Sound Road starting from Knapton Hill through to Middle Road in Flatts for approximately 27 weeks. The trench work will affect the westbound lane in sections of approximately 200 foot lengths at a time. The lane closure will be in effect day-and-night for the duration of this project and will be managed with traffic signs and signals.

Motorists are asked to avoid these lane closure sections and to use alternative routes via Devil’s Hole Hill, Knapton Hill or Harrington Hundreds Road for the duration of this trenching work. Signs will be placed to indicate detour routes.

Traffic controls will be under the direction of BELCO and Ministry of Public Works representative and will be managed through traffic control signals and detour signs.

The Ministry of Public Works wishes to encourage the full cooperation of the public and apologizes for any inconvenience that may result.

Should there be any questions regarding these works, please direct queries to the attention of Jonathan Pedro, Project Manager for BELCO at 295-5111 ext. 1441. Any queries on detour routes should be directed to Tina Beer-Searle, Civil Engineer Highways for the Ministry of Public Works on 501-3044.

By Order____________________________________________________

Lt. Col. the Hon. David A. Burch OBE [Mil] ED, JP, MP

Minister of Public Works

testimonial-divider

The official notices above have been republished from the relevant section on the official Government website. If you wish to view ‘hard copies’, the Department of Libraries & Archives prints them and you can visit the main library on Queen Street or the Government Archives in the Government Administration Building on Parliament Street to view them.